What Construction Failure Investigations Teach About Preconstruction Review

Lessons from official construction failure investigations for preconstruction and shop drawing review: why independent checks, acting on warning signs, and clear document control matter.

When a structure fails, official investigators examine what went wrong and why. Their findings are public, and they offer lessons that apply far beyond the specific incident. This article summarizes three documented cases, one during construction, one decades after construction, and one during reinforcement assembly, and discusses what they mean for preconstruction and shop drawing review.

The goal is not to assign blame or suggest that any single tool or process would have prevented a failure. It is to identify the kinds of checks and habits that investigators consistently highlight as important.

A documented case: the FIU pedestrian bridge (2018)

On March 15, 2018, a pedestrian bridge under construction at Florida International University in Miami collapsed onto the roadway below, killing six people. The National Transportation Safety Board (NTSB) investigated the collapse and published its findings in October 2019.

Source: NTSB Highway Accident Report HAR-19/02, adopted October 22, 2019.

What the investigation found

The NTSB determined that the probable cause of the collapse was errors in the load and capacity calculations for a critical connection (the 11/12 nodal region) made by the bridge's design firm. The design team underestimated the loads acting on that connection and overestimated its capacity, so the node could not resist the forces it actually carried.

Factors the NTSB cited:

  • Inadequate peer review by the independent review firm, which did not catch the calculation errors before construction.
  • Failure to recognize the significance of cracking that appeared in the structure before the collapse and to obtain an independent peer review of the remedial plan.
  • Contributing to the severity of the outcome: Failure by multiple parties on the project team to cease bridge work when cracking reached unacceptable levels and to close the road beneath the bridge to protect public safety.

What this was and was not

This was a design and peer review failure. The calculation errors were in the engineer's design, not in the fabrication or detailing of the reinforcement. The investigation does not attribute the collapse to rebar detailing, shop drawing errors, or field placement.

The lesson is not that better detailing would have prevented the collapse. It is that independent review at multiple stages, and a willingness to stop work when something looks wrong, are critical to catching errors before they cause harm.

A second documented case: Champlain Towers South (built 1981, partial collapse 2021)

On June 24, 2021, part of Champlain Towers South, a residential building in Surfside, Florida, collapsed, killing 98 people. The building had stood for about 40 years. The National Institute of Standards and Technology (NIST) investigated through its National Construction Safety Team and released technical findings on June 22, 2026. The final report with recommendations had not been published at the time of this update.

Sources: NIST technical findings announcement, June 22, 2026 and NIST video transcript of the technical findings.

What NIST reported

NIST found that the building had low margins against failure from the start, primarily because of two kinds of deviation:

  • Design deviations. The original structural design deviated in severe and widespread ways from the codes and standards of the day.
  • Construction deviations. What was built deviated from the design drawings. In the pool deck slab, NIST reported top reinforcement placed lower than specified (cover generally about 2 inches where the drawings showed 3/4 inch), fewer top bars passing over the columns than the design required, and top bar spacing near columns roughly 20 to 40 percent wider than the drawings called for.

NIST also reported that loads added over the years, such as planters and later pavers and sand, and long-term corrosion further reduced those margins, with corrosion most likely the final factor. NIST identified the initiating event as punching shear failure at two column connections in the pool deck slab in early June 2021. NIST noted that records of whether the construction changes were approved by the design engineer or observed by inspectors are not available.

What this was and was not

This collapse had multiple contributing factors: design deviations, construction deviations from the drawings, added loads, and corrosion. NIST's findings do not attribute the as-built reinforcement deviations to shop drawings, placing drawings, detailing, or any particular party, and NIST investigations do not assign fault or blame. The building did not fail during construction.

The lesson is not that any document or tool would have prevented the collapse. It is that the reinforcement in the concrete needs to match the current approved design documents, and any change from them needs documented approval from the engineer of record. Without those records, later investigators cannot tell whether a change was reviewed.

A third documented case: rebar dowel cage collapse during assembly (2020)

In April 2020, at a bridge construction site in British Columbia, vertical rebar dowel cages being tied to a purpose-built jig collapsed during assembly, seriously injuring two workers. WorkSafeBC, the province's workplace safety agency, published an incident investigation report summary in December 2021.

Source: WorkSafeBC Incident Investigation Report Summary, notice of incident number 2020178760013.

What the investigation found

WorkSafeBC identified the cause as inadequate temporary support. The employer's plan called for guylines and wire rope hoists to secure the cages during assembly, but they were not installed, and a WorkSafeBC engineer determined that the jig alone did not provide adequate lateral support. Contributing factors included incomplete hazard assessments, failure to follow safe work procedures, ineffective information and instruction, and inadequate supervision.

The summary notes that the employer had developed a shop drawing that also served as an assembly procedure, that additional stability measures planned to address concerns with that drawing were not implemented, and that the shop drawing and safe work procedures were not made available to the workers doing the work.

What this was and was not

This was a temporary support and site safety failure. The shop drawing in this case was the employer's assembly document, and WorkSafeBC does not attribute the collapse to placing drawings, bar lists, or detailing errors. In this case WorkSafeBC placed responsibility for temporary support on the employer, with the prime contractor also failing to ensure hazards were assessed.

The lessons for buyers are about scope and information flow. Some owners require a separate temporary support submittal for tall reinforcing assemblies; Caltrans, for example, lists shop drawings and design calculations for a temporary support system among reinforcement submittals (Caltrans Bridge Construction Memo 52-1). Confirm in scope review whether such a submittal applies and who prepares it. And drawings and procedures only help when the current version reaches the crew doing the work.

Themes that appear across investigations

Each case is specific, but the themes they highlight appear in many construction failure investigations:

1. Independent review catches what the original author misses

Calculations checked only by the person who wrote them are more likely to carry errors through to construction. Independent peer review, whether by another engineer, a third-party reviewer, or a checking engineer, provides a second set of eyes.

The same principle applies to shop drawings. When the detailer, the fabricator, and the engineer each review the package from their own perspective, errors are more likely to surface.

2. Warning signs in the field deserve serious attention

Cracking, deflection, or misalignment observed during construction may signal a problem in design, fabrication, or placement. Dismissing these signs, or delaying action while they are evaluated, can allow a small problem to become a catastrophic one.

For shop drawing and detailing work, the parallel is simpler: when the field or the shop reports a conflict, a bar that does not fit, or a detail that does not match the structural intent, that question deserves a prompt answer.

3. Document control and revision tracking matter

When different parties work from different versions of drawings, or revisions are not clearly communicated, confusion about which document is current can propagate errors or undo corrections.

Clear revision control, revision clouds, and explicit references to the structural set revision level help everyone work from the same information.

Two of the cases above touch this theme directly. NIST could not find records showing whether the Champlain Towers South construction changes were approved, and in the WorkSafeBC case the shop drawing and procedures did not reach the crew.

4. Field deviations need documented approval

When what is built differs from the approved documents, the change should go back to the engineer of record and be recorded. That record is what lets anyone, years later, tell a reviewed change from an unreviewed one.

What this means for shop drawing review

Shop drawings and placing drawings are not the same as design calculations, and detailers are not responsible for the engineer's design. But the review process for submittals is one of the checkpoints where errors can be caught before steel is fabricated.

The themes above suggest a few habits:

  • Take review seriously. A submittal that is rubber-stamped without examination is a missed opportunity to catch a conflict or a misinterpretation.
  • Act on comments. When the engineer marks something "revise and resubmit," the revision matters. Applying it to one sheet and missing it on another creates exactly the kind of drift that investigators flag.
  • Track revisions visibly. Revision logs, clouds, and dated transmittals help everyone know what version is current.
  • Raise questions early. An RFI sent during detailing is cheaper than a problem found during placement. For more on this, see How Rebar RFIs Cause Project Delays.
  • Get current documents to the people doing the work. An approved drawing does not help a crew that never sees it.
  • Send field deviations back for approval. If reinforcement cannot be placed as drawn, the answer should come from the engineer of record and be documented.

Limitations

This article draws on three official investigations. It does not claim that the themes apply to every project or that any specific tool or workflow would have changed the outcome of any of these incidents. The NIST investigation of Champlain Towers South is ongoing, and its final report may refine the technical findings summarized here. Official investigations are conducted by trained professionals with access to evidence that is not publicly available. This summary is based only on the published materials.