When the project documents require reinforcing shop drawings to be reviewed before fabrication, that review sits between design and the first pour. Delays in it can move fabrication and pour dates.
This guide explains what happens during the approval cycle, where delays come from, and what project teams can do to keep the process moving.
The approval sequence
Who approves rebar shop drawings?
A rebar detailer prepares the shop drawings, they are usually sent through the general contractor, and the engineer of record reviews and approves them before fabrication.
One example sequence is below. The project documents define the actual routing and reviewers.
- Detailer produces shop drawings (placing drawings and bar bending schedules) from the structural documents.
- Fabricator or GC reviews the package for completeness and coordination.
- GC transmits the submittal to the engineer of record (or the engineer's designated reviewer).
- Engineer reviews for conformance with design intent and marks up any issues.
- Detailer revises based on comments.
- Engineer re-reviews (if "revise and resubmit" was the first response).
- Approved package is released to the fabricator.
- Fabricator cuts, bends, and ships the steel.
Each step has a contractual or practical turnaround. When any step takes longer than planned, the downstream steps shift, and the pour date moves with them.
Where delays happen
Engineer review backlog
Engineers review submittals alongside their other work. If a firm is short-staffed or handling multiple projects, your package waits in a queue. Use the review periods stated in the applicable project documents when planning the submittal schedule.
Revise and resubmit cycles
A "revise and resubmit" response means the package goes back to the detailer, then back through the GC, then back to the engineer. Each cycle adds days or weeks. Some owners, for example the City of Los Angeles, require revised drawings to be resubmitted and accepted before fabrication can proceed. Multiple cycles on the same pour can push the schedule significantly.
RFIs embedded in the submittal
When the detailer raises questions in the submittal (or the engineer marks items that require clarification), the approval waits on the RFI response. For more on how RFIs compound delays, see How Rebar RFIs Cause Project Delays.
Incomplete or inconsistent submittals
Packages that are missing sheets, have mark mismatches, or cite the wrong structural revision get bounced back before the engineer even reviews the bars. That lost cycle is pure waste.
Coordination gaps
If the submittal arrives without input from the fabricator, or if the GC does not review before transmitting, errors that could have been caught internally end up in the engineer's hands. The scope of the engineer's review is set by the project documents, so coordination errors are best resolved before the package is transmitted.
The cost of approval delays
Fabrication queue slips. Fabrication is planned around released drawings. A late approval can cost a job its planned slot in the fabrication schedule.
Pour dates move. Concrete pours are sequenced. When one pour slips, the pours behind it often have to resequence, which affects crane time, crew scheduling, and formwork.
Expediting costs. Rush fabrication and overtime shipping to recover lost time are expensive.
Idle crews. Ironworkers standing by for steel that has not arrived cost money even when they are not placing bars.
Compressed field time. When the schedule is squeezed, the field has less time to place and inspect, which raises the risk of errors that cause their own delays.
What project teams can do
Build review time into the schedule realistically
If the specification allows 14 days for engineer review and you have planned for 7, the schedule is already behind. Plan for the time the contract actually allows, plus buffer for at least one revision cycle.
Submit early and in phases
The first pour is often the simplest (footings, foundations). Get that submittal in early so approval delays do not stack behind design questions on later, more complex pours.
Review internally before transmitting
The GC and fabricator should review the package before it goes to the engineer. Catching a missing sheet or a mark mismatch at this stage saves a full review cycle. On U.S. federal projects, for example, FAR 52.236-21 requires the contractor to coordinate shop drawings and review them for accuracy, completeness, and compliance with contract requirements, and the Contracting Officer's approval does not relieve the contractor of responsibility for errors or omissions in them.
Track submittals visibly
Everyone on the team should know where each submittal is: with the detailer, with the engineer, waiting on an RFI, or released. Surprises happen when packages sit in someone's inbox unnoticed.
Communicate with the engineer
If the engineer is overloaded, knowing that early lets you adjust the schedule or escalate. A quick call is often more effective than a formal letter.
Invest in cleaner first submittals
Detailing that is consistent, complete, and matches the current structural revision is more likely to be approved on the first pass. The detailer's quality and the time spent on internal QC pay off in fewer cycles.
The role of deliverable clarity
Sometimes delays come from ambiguity about what the submittal should include. Mismatched expectations between detailer, fabricator, GC, and engineer create extra rounds of clarification.
Agreeing on included deliverables and review rounds when you buy detailing helps; see What Drives Rebar Detailing Cost and How to Compare Quotes.
For more on what rebar deliverables contain and how they differ, see Placing Drawings vs. Shop Drawings vs. Bar Lists.
Comparing detailing approaches
No detailing approach changes the review period set in the project documents. When comparing providers, manual or automated, ask how revisions are carried through drawings and schedules together and what resubmittal turnaround they will commit to in writing.